Construction of Huizhou No.1 Highway AlmostCompleted

图片1.png

Workers are maintaining the precast girders at the No. 7 precast girder making site.

  The 丰-shaped transportation project is one of the top 10 major infrastructure projects for Huizhou municipal government this year. As an important vertical line of this 丰-shaped transportation system, Huicheng-Xiachong highway, also known as the No.1 highway, is speeding up its construction. As of now, the budgeted cost for work performed for the No.1 highway has reached 75% of the total, with 90% of the roadwork being completed.

  Cast-in-situ concrete process begins at Xizhijiang Bridge

  Cast-in-situ concrete process begins at Xizhijiang Bridge, which is one of the two cross-river bridges for the No.1 highway project. The bridge, with a length of 613, has eight lanes in both directions, non-motorized lanes and sidewalks on both sides. At the construction site dozens of workers are seen tying brackets. According to Mr. Li Qiuping, project manager of Huizhou Huiwan Highway Co., Ltd, the construction for the bridge first began at early 2023, as of now the bridge piles, bearing platforms, piers and cover beams have been completed, and the construction team will accelerate the cast-in-situ concrete process in the near future.

  No. 1 highway is divided into three sections for construction, of which Section B is located in Shuikou Sub-district  and Ma'an Township, Huicheng District, with a total length of 16.5 kilometers, mainly elevated bridges, with a length of 11.39 kilometers of bridges. Piles of precast girders are seen at the No.7 precast girder making site, and these girders will then be delivered to the construction sites of Dahuxi super-bridge and Weiling.

  According to Mr. Chen Zhongyao, project manager of Section B, there are six girder production yards in Section B, with the daily capacity of 20 prefabricated girders. At present, Section B has completed the bridge pile foundation, bearing platform, pier column and most of the cover girder construction, and greater efforts will be made to carry out prefabricated girder production and girder erection work in full scale, thus laying a good foundation for the bridge project and the roadbed project construction.

  The main bridge will have 8 lanes in both directions.

  No. 1 highway is not only the “spine” of the 丰-shaped transportation network, but also an important step for Huizhou to implement the strategy of integrating its development with Shenzhen and the Greater Bay Area. The total mileage of the project is about 69.9 kilometers, of which 64.52 kilometers is the length of the main line and 5.38 kilometers is the length of the Shuikou branch line.

  The main line of the project starts from Chizhukeng Village of Boro County, with a direct connection with the Guangzhou-Huizhou Expressway, passes through Luoyang Sub-district of Boro County, Xiaojinkou Sub-district of Huicheng District, Ruhu Town, Shukou Sub-district, Ma'an Town, Yonghu Town of Huiyang District, Liangjing Town, Baihua Town of Huidong County, and finally reaches the Chengtiankeng Village of Xiachong Sub-district in Daya Bay Development Zone, where the project connects with the Huishen Coastal Highway. Shuikou Branch Line starts from Niulutou Village, Huicheng District, connecting with the main line of No.1 highway 1, and finally ends at Zhuwu Village of Shuikou Sub-village in Huicheng District, where the project connects with Huizhou-Daya Bay Expressway. The No. 1 highway is designed to build a two-way eight-lane highway, with a design speed of 100 kilometers per hour; the ShuiKou branch line is designed to build a two-way six-lane highway, with a design speed of 100 kilometers per hour.

  According to Mr. Li Qiuping, “The construction of No. 1 highway began in October 2023, and as of now the roadway is nearly 90% completed, culverts 98% completed, bridges 70% completed, tunnels 92.13% completed and pavement 17.54% completed.” All the participants of No.1 highway will make all necessary measures to ensure the quality of the project, accelerate the construction of the project in accordance with the timetable, and make sure that the highway will be open to traffic on time.

Reported by: DAI Jian