CHN Energy Huizhou Power Plant Phase II Achieved Successful Completion and Commissioning

图片1.png

Phase II of CHN Energy Huizhou Power Plant 。Taken by Zeng Jingyan and Zhang Chao


“10, 9, 8...3, 2, 1.” At 11:11 AM on October 18th, a burst of enthusiastic applause and cheers erupted in the control room of the Phase II of CHN Energy Huizhou Power Plant, as the countdown on the big screen came to an end, marking a successful completion of the 168-hour full-load trial operation for the set of four-generation units. 

Following the completion and commissioning of the three units on October 7th, the project achieved the “dual-unit commissioning” target within a month. This marks the full completion and commissioning of the first gas-fired power station invested and constructed by the CHN Energy in the Guangdong-Hong Kong-Macao Greater Bay Area. The CHN Energy Huizhou Power Plant has now become a power station with a capacity of one million kilowatts. The two gas-fired generation units in the second phase can achieve a capacity of an annual power generation of 3.93 billion kilowatt-hours and a heat supply of 7.27 million gigajoules, effectively meeting the diverse energy needs of the Daya Bay Petrochemical Park and promoting the green and low-carbon transformation of regional energy supply.

Going Digital

Building a “Digital Twin Power Station” for the Entire Lifecycle

As a major project for electricity supply and a priority in energy construction in Guangdong Province, the newly constructed 2x500-megawatt “gas-steam” combined cycle units of the Phase II of CHN Energy Huizhou Power Plant is the first gas-fired cogeneration project to be completed and put into operation after the reorganization of the CHN Energy Group. The project started construction on September 28, 2022, and has achieved the goal of full-scale production after more than 750 days. During the construction period, having overcame numerous difficulties, like heavy rain and humidity, high temperatures and typhoons, as well as torrential rain and flooding, builders completed node projects, such as basic infrastructure setup, main plant enclosure, gas turbine installation, waste-heat boiler lifting, plant power reception, first ignition, and first grid connection, with high quality and efficiency. They also met deadlines for external projects such as power transmission, gas pipelines, and heating networks. All these efforts laid a solid foundation for the smooth completion and production of the entire project.

The project is also a testament to the exploration of “digital” technology applications, showcasing the integration of technology and craftsmanship. As a dual demonstration project for “domestic BIM” and “digitalization” within the CHN Energy Group, the Phase II project of CHN Energy Huizhou Power Plant has not only constructed a physical power plant but also nurtured a “digital twin brother” for the power plant in the virtual space. Relying on the construction of Phase II, the plant has carried out research and construction for demonstration application on key digital technologies for thermal power engineering (gas-fired) based on domestically controlled BIM, and pioneered the gradual delivery of digital twin for gas-fired power stations. “The 3D model on this digital platform is our virtual power plant. It shares the same origin with the physical power plant, supporting each other and growing synchronously. This is the ‘Digital Twin Power Station’ we have created,” said the responsible person for the plant’s Phase II project.

In the central control room of the Phase II of CHN Energy Huizhou Power Plant, power plant operators are monitoring various operational data of the equipment in real time on large screens. All data information during the “growth” process of the power plant is accurately recorded. The project integrates data from various sources throughout the entire lifecycle of the project, covering five processes: “fully professional visualization collaborative design, all-element intelligent engineering management, full-series digital 3D delivery, whole-process smart production and operation, and whole-life big data digital twin.” It integrates data such as safety, personnel, security, ubiquitous perception, fire protection, and electrical monitoring, which can achieve automation in the execution process of the power plant, intelligent in the management process, and intelligence in business management and decision-making.

Having achieved the promotion and application of domestic BIM technology throughout the entire lifecycle of gas-fired power station projects, the construction of the Phase II of CHN Energy Huizhou Power Plant has established a set of information model application standards, a set of basic technical application research reports, and a series of digital demonstration applications in the field of gas-fired power station engineering. The project has won a total of 7 provincial and ministerial awards, 16 association-level awards, obtained 10 utility model patents, 1 invention patent, and authorized 40 software copyrights. It has published 5 scientific papers, participated in the compilation of 1 industry-level standard, and 6 corporate standards within the group.

Use It Wisely

Carbon dioxide emissions are half of those of traditional coal-fired power plants.

From “coal-fired power” to “gas-fired power,” gas-fired power plants are not only energy-efficient and high-output but also more environmentally friendly. After full-scale operation, the two gas-fired units of the Phase II of CHN Huizhou Power Plant can achieve an annual power generation of 3.93 billion kilowatt-hours and a heat supply of 7.27 million gigajoules, with comprehensive efficiency of energy utilization of 75.51%. Owing to the use of clean energy, such as natural gas, and high combustion efficiency, the emissions of pollutants are relatively low, and the carbon dioxide emissions are only about 50% of that of a coal-fired power plant of the same installed capacity.

The production equipment of the Phase II of CHN Energy Huizhou Power Plant also embodies the concept of energy saving and environmental protection in every aspect: By installing an expanded economizer at the rear of the waste heat boiler, the waste heat from the flue gas is used to produce hot water (43t/h) to supply to the hot water type lithium bromide cooling units, which can reduce the flue gas temperature by nearly 3℃, achieving an annual saving of approximately 880,000 yuan in plant electricity consumption. Effluent from domestic sewage, cooling tower blowdown, boiler blowdown, and the concentrate from the first stage of reverse osmosis (RO) are all collected and reused within the plant. Industrial wastewater, like flushing wastewater from the main plant building, is treated and then connected to the industrial wastewater treatment station. Oil-containing wastewater is collected and discharged into the emergency oil sump, and connected to the existing oil-containing wastewater treatment system built in Phase I for treatment, achieving zero wastewater discharge from the entire plant.

For the project to play as a “stabilizer” and a “ballast stone” for energy supply, flexibility is a key capability for the Phase II of CHN Energy Huizhou Power Plant. As one of the main power sources for the Huizhou 220kV and below power grid, the Phase II of CHN Energy Huizhou Power Plant can enhance the power support capacity of the grid. Since the gas-steam combined cycle units can be quickly started and stopped, adapting to rapid changes in grid load, the gas units have characteristics of strong peak regulation capabilities and flexible operation. They can quickly adjust the power generation according to changes in electricity demand, thus helping to alleviate the contradiction between electricity supply and demand. During peak power demand periods, they can play a role in emergency peak regulation, ensuring a safe and stable power supply. 

“Next, by fully leveraging the integrated and comprehensive advantages of its Phase I coal-fired units and Phase II gas-fired units, CHN Energy Huizhou Power Plant will meet the diverse needs of heat users in the Daya Bay Petrochemical Park through high, medium, and low-pressure steam ‘triple supply’ and enhance the park’s comprehensive energy service level and energy utilization efficiency for electricity, heat, cooling, and gas,” said the responsible person for the Phase II project. At the same time, based on the demonstration application of Phase II, CHN Energy Huizhou Power Plant will analyze the bottlenecks in the production process, push for the digital transformation of the enterprise in terms of resource allocation, business operations, decision-making mechanisms, and business models, improve efficiency, reduce costs, and explore more new models for the construction of future digital and intelligent power plants.

Reported by: ZENG Jingyan, ZHANG Chao