Hot Functional Testing Completed for Unit 1 at Taipingling Nuclear Power Plant

图片1.png

Unit 1 and 2 of Taipingling Nuclear Power Plant are expected to be operational next year

According to CGN Huizhou Nuclear Power Co., Ltd, hot testing for Unit 1 at Taipingling Nuclear Power Plant was completed on September 15th. The reactor unit will now be ready for subsequent commissioning steps including fuel loading and initial reactor startup.

Taipingling nuclear power project is the first ecological nuclear power construction demonstration project in China. Hot testing usually takes place over several weeks and consists of multiple tests performed on major systems to check their performance under normal operational conditions, without any nuclear fuel assemblies in the reactor. At the same time, the testing will enable operators to further familiarize themselves with the operation of the power plant through the test process to ensure the safe and stable operation of the nuclear power unit, which is a milestone construction node of the nuclear power plant project.

The completion of the hot functional testing of Unit 1 means that all systems perform well in the hot state and are ready for subsequent operation. According to CGN Huizhou Nuclear Power Co., Ltd, on the basis of the previous projects, Taipingling Nuclear Power Project has carried out dozens of adjustments and optimizations, such as optimization of main parameters, optimization of layout of refueling water tank inside containment vessel, and independent design of steam generator, and carried out the domestic application of major equipment such as steam generator, turbine control system platform, pressurizer spray valve, and main steam safety valve for the first time. The project showcases the comprehensive strength of CGN in technological innovation and market expansion, and has accumulated key technical indicators and engineering experience for the mass construction of CGN “Hualong One”.

According to the original plan, unit 1 of the first phase of the Taipingling nuclear power project will start power generation at the beginning of next year, while the unit 2 will start the loading and grid connection next year. It is expected that each unit can generate 10 billion KWH of electricity, which can effectively promote local economic development, ensure energy security, optimize the energy structure, and protect the ecological environment.

Reported by: FENG Lijun, YANG Yang

Editor:   Time:2024-09-19
   
   